Draft progress claim
INV-2026-4232
Claim no. 4 · 26% of contract
Scheduled 08 Nov 2026 · Due 08 Dec 2026
| Item | Description | Item value (ex) | Claimed to date | This claim (ex) |
|---|---|---|---|---|
| 1 | Balustrade 1 — mezzanine edge balustrade (64 m) | $94,705.55 | 100% | $24,868.55 |
| 2 | Balustrade 2 — stair balustrade, hangar office (38 m) | $58,786.35 | 70% | $15,436.60 |
| 3 | Handrails — galvanised to apron access (90 m) | $33,491.00 | 70% | $8,794.34 |
| 4 | External bollards — galvanised, apron (24 no) | $27,277.20 | 50% | $7,162.67 |
| 5 | Perforated panelling — plant screen enclosure | $71,381.65 | 40% | $18,743.97 |
| 6 | Ships ladders, cages & roof access platform | $56,442.45 | 10% | $14,821.11 |
| 7 | Grating walkways & landings — services gantry | $83,497.70 | 0% | $21,925.50 |
| V | V1 — Additional galvanised bollards to apron (6 no)variation | $10,654.00 | 0% | $2,797.61 |
| Contract value (ex GST) | $436,235.90 |
| Previously claimed (48%) | $207,135.22 |
| This claim (26%) | $114,550.35 |
| Claimed to date | $321,685.57 |
| Remaining to claim | $114,550.33 |
| Subtotal (ex GST) | $114,550.35 |
| GST 10% | $11,455.04 |
| Total (inc GST) | $126,005.39 |
Payment by EFT — Co-Create Solutions Pty Ltd · BSB 105-085 · Account 0472 51830
Please quote INV-2026-4232 and PO HY-AIR7-PO-4471 as the reference. Terms NET 45.
This claim is lodged through PayApps.
Please quote INV-2026-4232 and PO HY-AIR7-PO-4471 as the reference. Terms NET 45.
This claim is lodged through PayApps.
Co-Create Solutions · Engineering & fabrication partner · cocreate.net.au