26-1063 · PRJ-2026-414

Marine handrail & ladder package
Demo 05 Oct 2026
← Register
26-1063 PRJ-2026-414 Complete Complete MYOB

Marine handrail & ladder package

Client Badge Constructions Site Kent Town SA PM Matthew Warren Client PO BC-24-1187 Programme 03 Aug 2026 → 26 Aug 2026 Quote Q-2026-1063
Progress100%
Contract value (ex GST)
$308.3k
4 items
Claimed to date
$308.3k
100% of contract
Scheduled claims (draft)
$0
0 staged · MYOB
Gross profit (items)
30.1%
from quote-book costings
Allowed / actual hours
1752 / 1711
factory · site · office
ItemsHours shown allowed / actual · bar turns red when over the allowance
ItemDescriptionStatusValue%ClaimedClient PO Factory hSite hOffice hDue w/cJob card · ITP
1 Balustrade — marine handrail & ladder package $77,135.05 25% 100% · $77.1k BC-24-1187
233 / 230
151 / 142
54 / 54
24 Aug —
2 Handrails — marine handrail & ladder package $77,135.05 25% 100% · $77.1k BC-24-1187
233 / 223
151 / 151
54 / 51
24 Aug —
3 Access platform — marine handrail & ladder package $76,703.05 24.9% 100% · $76.7k BC-24-1187
233 / 225
151 / 154
54 / 56
24 Aug —
4 Stair & landings — marine handrail & ladder package $77,351.05 25.1% 100% · $77.4k BC-24-1187
233 / 226
151 / 148
54 / 51
24 Aug —
Progress claims$308,324.20 claimed · $0.00 scheduled
Claim%DateAmount (inc GST)ChannelSyncStatus
#1 · INV-2026-4244 50% 13 Aug 2026 $169,578.31 MYOB Pushed to MYOB Paid
#2 · INV-2026-4245 50% 20 Aug 2026 $169,578.31 MYOB Pushed to MYOB Paid
Weekly project meetings
No minutes recorded yet.
Purchase orders8 · $76,272.00 ex GST
POSupplierItemDateSubtotalStatus
PO-2026-7165 Coventry Fasteners 1 12 Aug 2026 $3,816.00 Received
PO-2026-7167 Coventry Fasteners 2 09 Aug 2026 $3,816.00 Received
PO-2026-7166 InfraBuild Steel Centre 2 08 Aug 2026 $15,252.00 Received
PO-2026-7171 Coventry Fasteners 4 07 Aug 2026 $3,816.00 Received
PO-2026-7169 Coventry Fasteners 3 06 Aug 2026 $3,816.00 Received
PO-2026-7168 Southern Steel Group 3 06 Aug 2026 $15,252.00 Received
PO-2026-7164 Bianco Steel 1 06 Aug 2026 $15,252.00 Received
PO-2026-7170 Bianco Steel 4 05 Aug 2026 $15,252.00 Received
Recent labourlast 15 clock-ons
DatePersonItemKindHours
26 Aug 2026 Sam Nguyen 2 Office 3
26 Aug 2026 Peter Voulgaris 1 Factory 8
26 Aug 2026 Ryan Tsoukalas 2 Factory 8
26 Aug 2026 Ryan Tsoukalas 2 Factory 7
26 Aug 2026 Mitch Daly 3 Factory 8
26 Aug 2026 Ryan Tsoukalas 3 Factory 8
26 Aug 2026 Josh Kerr 4 Factory 8
26 Aug 2026 Anthony Reid 4 Factory 2
26 Aug 2026 Kyle Mancini 1 Site 8
26 Aug 2026 Tyler Hocking 2 Site 8
26 Aug 2026 Ben Hartley 3 Site 8
26 Aug 2026 Kyle Mancini 4 Site 8
25 Aug 2026 Yang Li 2 Office 8
25 Aug 2026 Anthony Reid 1 Factory 8
25 Aug 2026 Josh Kerr 2 Factory 8
Crew assigned
No one assigned yet.
Open the shift schedule →
SWMSNot started
No SWMS submitted to the client for this project.
Prepared in JSEasy · submitted to and accepted by Badge Constructions. Compliance →
SharePointSynced
Co-Create › Projects › 26-1063 Badge Constructions — Marine handrail & ladder package
  • 01 Enquiry & Tender
  • 02 Quote Book
  • 03 Drawings (SolidWorks)
  • 04 Purchasing
  • 05 QA & ITPs
  • 06 Safety & SWMS
  • 07 Progress Claims
Client
Badge Constructions
Nick Karagiannis · nick@badgeconstruct.com.au
Kent Town SA · NET 30